athenaprep

Menu

HomeLearnPracticeAthena RC LabRC 99 & CR 101Daily FlashcardsPYQsMocks
Syllabus Progress TrackerMock TrackerAnalytics
1:1 MentorshipAthena ArcadeQuantify CATFocusRevision Resources
Percentile PredictorCutoff PredictorMBA ProfilizerMBA Entrance ExamsTop MBA CollegesWAT-PI & Counselling
Refer & Earn
athenaprep

Menu

HomeLearnPracticeAthena RC LabRC 99 & CR 101Daily FlashcardsPYQsMocks
Syllabus Progress TrackerMock TrackerAnalytics
1:1 MentorshipAthena ArcadeQuantify CATFocusRevision Resources
Percentile PredictorCutoff PredictorMBA ProfilizerMBA Entrance ExamsTop MBA CollegesWAT-PI & Counselling
Refer & Earn
AProfile
athenaprepPractice free
PYQsCAT Quantitative AbilityTime and Work

CAT Time and Work Questions & Solutions

A sample of real CAT Time and Work past-year questions, each with a worked solution and the correct answer highlighted. AthenaPrep has 45 Time and Work questions in all — sign up free to practise them timed.

  1. Q1.CAT 2025

    Arun, Varun and Tarun, if working alone, can complete a task in 24, 21, and 15 days, respectively. They charge Rs 2160, Rs 2400, and Rs 2160 per day, respectively, even if they are employed for a partial day. On any given day, any of the workers may or may not be employed to work. If the task needs to be completed in 10 days or less, then the minimum possible amount, in rupees, required to be paid for the entire task is

    • 38400

    • 38880

    • 34400

    • 47040

  2. Q2.CAT 2025

    Ankita is twice as efficient as Bipin, while Bipin is twice as efficient as Chandan. All three of them start together on a job, and Bipin leaves the job after 20 days. If the job got completed in 60 days, the number of days needed by Chandan to complete the job alone, is

    Answer: 340

  3. Q3.CAT 2023

    The amount of job that Amal, Sunil and Kamal can individually do in a day, are in harmonic progression. Kamal takes twice as much time as Amal to do the same amount of job. If Amal and Sunil work for 4 days and 9 days, respectively, Kamal needs to work for 16 days to finish the remaining job. Then the number of days Sunil will take to finish the job working alone, is

    Answer: 27

  4. Q4.CAT 2022

    Working alone, the times taken by Anu, Tanu and Manu to complete any job are in the ratio 5 : 8 : 10. They accept a job which they can finish in 4 days if they all work together for 8 hours per day. However, Anu and Tanu work together for the first 6 days, working 6 hours 40 minutes per day. Then, the number of hours that Manu will take to complete the remaining job working alone is

    Answer: 6

  5. Q5.CAT 2021

    Amar, Akbar and Anthony are working on a project. Working together Amar and Akbar can complete the project in 1 year, Akbar and Anthony can complete in 16 months, Anthony and Amar can complete in 2 years. If the person who is neither the fastest nor the slowest works alone, the time in months he will take to complete the project is

    Answer: 32

  6. Q6.CAT 2021

    One day, Rahul started a work at 9 AM and Gautam joined him two hours later. They then worked together and completed the work at 5 PM the same day. If both had started at 9 AM and worked together, the work would have been completed 30 minutes earlier. Working alone, the time Rahul would have taken, in hours, to complete the work is

    • 11.5

    • 10

    • 12.5

    • 12

  7. Q7.CAT 2019

    Anil alone can do a job in 20 days while Sunil alone can do it in 40 days. Anil starts the job, and after 3 days, Sunil joins him. Again, after a few more days, Bimal joins them and they together finish the job. If Bimal has done 10% of the job, then in how many days was the job done?

    • 12

    • 13

    • 15

    • 14

  8. Q8.CAT 2018

    When they work alone, B needs 25% more time to finish a job than A does. They two finish the job in 13 days in the following manner: A works alone till half the job is done, then A and B work together for four days, and finally B works alone to complete the remaining 5% of the job. In how many days can B alone finish the entire job?

    • 20

    • 22

    • 16

    • 18

  9. Q9.CAT 2018

    Ramesh and Ganesh can together complete a work in 16 days. After seven days of working together, Ramesh got sick and his efficiency fell by 30%. As a result, they completed the work in 17 days instead of 16 days. If Ganesh had worked alone after Ramesh got sick, in how many days would he have completed the remaining work?

    • 14.5

    • 11

    • 13.5

    • 12

  10. Q10.CAT 2017

    Amal can complete a job in 10 days and Bimal can complete it in 8 days. Amal, Bimal and Kamal together complete the job in 4 days and are paid a total amount of Rs 1000 as remuneration. If this amount is shared by them in proportion to their work, then Kamal's share, in rupees, is

    • 100

    • 200

    • 300

    • 400

  11. Q11.CAT 2001

    A can complete a piece of work in 4 days. B takes double the time taken by A, C takes double that of B, and D takes double that of C to complete the same task. They are paired in groups of two each. One pair takes two-thirds the time needed by the second pair to complete the work. Which is the first pair?

    • A and B

    • A and C

    • B and C

    • A and D

  12. Passage

    The Weirdo Holiday Resort follows a particular system of holidays for its employees. People are given holidays on the days where the first letter of the day of the week is the same as the first letter of their names. All employees work at the same rate.
    Q12.CAT 1997

    Starting on February 25, 1996 (Sunday), if Raja had finished his job on April 2, 1996, when would T and S together likely to have completed the job, had they started on the same day as Raja?

    • March 15, 1996

    • March 14, 1996

    • March 22, 1996

    • Data insufficient

33+ more Time and Work questions inside

Get the full CAT Time and Work set with timed practice, bookmarks and analysis — free to start.

Start practising free

CAT Time and Work previous year questions with solutions — AthenaPrep